Uncategorized

Should You Make Meetings of CEOs a Condition to Arbitration?

This is Part 3 in a 20-part series of articles dealing with issues of arbitration, mediation and alternate dispute resolution in the construction industry.

Over the last decade, a requirement has slipped into the dispute resolution clauses of many construction contracts requiring the CEOs of the various parties to meet as a condition precedent to any arbitration. If something is a “condition precedent” and the contract uses those specific terms, then the meeting must occur before a party can either demand arbitration or file litigation.

Since the parties negotiate their contract, the question becomes whether this is a prudent requirement to place in the contract. The answer is, in most instances, yes. Often times, the parties’ representatives who are involved in the dispute are not the CEOs of the companies. The CEOs, generally speaking, have cooler heads when it comes to resolving heated disputes. They may be one step removed. Forcing the CEOs to meet and discuss the claim has a general influence on either resolving the disputes or substantially narrowing them.

Contractor Stung By Liquidated Damages

The recent case of Abhe & Svboda Inc. v MDOT (Court of Appeals, August 2017), underscores the difficulty in challenging Liquidated Damages, particularly where a contractor does not comply with delay claim provisions.

This case arose from the late completion by Abhe & Svboda, Inc (ASI) of a contract with the Michigan Department of Transportation (MDOT) to clean and paint part of the Mackinac Bridge. The contract specified Liquidated Damages (LDs) of $3,000 a day for each day of late completion. The contract also gave ASI the right to seek a time extension for bad weather, provided that ASI asserted the request within the time period required by the contract. ASI did not timely complete the project and the State assessed LDs of about $1.9 million for being 644 days late.

ASI sued the State challenging the LDs assessment for a number of reasons. For instance, ASI argued that the LDs should not apply to 362 days of the planned winter shutdown during which it was impossible for MDOT to suffer any losses and that the LD clause was void for failing to be a good-faith effort to estimate losses. ASI also argued that MDOT’s dilatory behavior in approving ASI’s scaffolding plan caused 56 days of delay. ASI argued that 459 days of work were caused by environmental circumstances beyond its control. The trial court rejected all of ASI’s arguments and granted summary disposition to the State. ASI appealed.

Construction Disputes: Arbitration or Litigation?

This is Part 1 in a 20-part series of articles dealing with issues of arbitration in the construction industry.

The question of whether to arbitrate or litigate disputes comes up fairly frequently in the construction industry. From my humble perspective, with respect to construction disputes, there are very few circumstances where I would choose litigation over arbitration. Why?

Choice of Decision Maker
With arbitration, in general, you pick the decision maker(s) as opposed to being assigned a judge through a blind draw in the court system. That level of arbitrator selection may range from picking from a list under the American Arbitration Association Rules to hand picking a blue-ribbon panel of arbitrators or even a single arbitrator through private arbitration. If you are assigned a judge through the courts, you may end up with a judge who does criminal proceedings in the morning, divorce proceedings before lunch, and then handles your complex construction law dispute in the afternoon, in 15-minute increments, along with multiple other disputes in what looks to an outsider like a giant cattle call. Unless your contract provides otherwise, you may also be in the unlucky position to try your complex construction disputes to a jury.

Construction Contract Clauses, Part 3 – Site Investigation Clauses

A site investigation clause is a provision in a construction contract that indicates that one of the parties has made an inspection of the property, project, or location where certain services, labor, or material will be provided, and that the party making the inspection is satisfied that performance will be possible given the circumstances. The following is an example of a site investigation clause:

Each contractor shall examine the construction site and area and compare its findings with the Drawing and Specification and shall inform and satisfy itself as to all matters necessary for carrying out the work; including but not limited to, general working conditions, labor and equipment requirements, accessibility, condition of the premises, obstructions, drainage conditions, actual levels, excavating, filling, etc. The Contractor shall investigate all conditions as to character of the site and character of existing structures at or adjacent to the site, and the character and extent of the Owner’s and other Contractors’ operations in the area, and in connection with the project, and shall take all such matters into account in submitting its bid. No allowance or extra payment will be subsequently made because of any such items or conditions occasioned by the Contractor’s failure to make such comparison and examination or on account of interferences from the Owner’s, Construction Manager’s and other Contractors’ activities, or by reason of any error or oversight on the Contractor’s part.

Court Enforces Subcontractor’s Obligation to Indemnify Contractor

The Michigan Court of Appeals recently affirmed a contractor’s right to defense and indemnity from its subcontractor under the plain language of the parties’ subcontract. Provenzino v Macomb County Department of Roads, et al (January 2017).

In this case, Mr. Provenzino alleged that he was injured when he fell from his motorcycle after encountering a disparity in height between adjacent milled and unmilled lanes of traffic in a construction zone. Provenzino sued multiple parties including Florence Cement Company, the general contractor, and Lois Kay Contracting Company (LKCC), the subcontractor who milled the roadway surfaces. Florence filed a cross claim against LKCC seeking indemnity based upon the indemnification provision in the parties’ subcontract. That provision stated:

Subcontractor agrees, and shall bind all sub-subcontractors to agree to indemnify Contractor, Owner and all other parties the Contractor is obligated to indemnify pursuant to the Prime Contract (hereinafter “Indemnitees”), and to defend and hold Indemnitees forever harmless from and against all suits, actions, legal and administrative proceedings, claims, demands, damages, interest, attorney fees, costs and expenses of whatsoever kind or nature whether arising before or after completion of Subcontractor’s work and in any manner directly or indirectly caused or claimed to be caused by any action or negligence of Subcontractor or Sub-subcontractor, and regardless whether directly or indirectly caused or claimed to be caused in part by a party indemnified hereunder or by anyone acting under their direction, control or on their behalf, until such time as a judgement [sic] is entered against Contractor by a court of law. …[emphasis added].

New Overtime Rule – Legal Implications for Employers

In May 2016, the Department of Labor (DOL) released its long-anticipated new overtime rule for Executive, Administrative, and Professional employees. These employees are generally your managers and white-collar professionals. If these employees perform certain “duties” (as defined by DOL regulations) and are paid a salary, then you do not need to pay them overtime. They are referred to as “salaried exempt” (ie, exempt from overtime laws).

As of December 1 of this year, these Executive/Administrative/Professional employees will need to be making at least $47,476 annually (or $913 per week) in order to qualify as “exempt” from overtime. Right now, the required salary threshold is only $23,660 (or $455 per week). Under the new rule, up to 10 percent of the salary can include nondiscretionary bonuses, incentive payments, and commissions.

Supplier Who Does Everything Right Wins Big on Payment Bond Claim

Supplier Who Does Everything Right Wins Big on Payment Bond Claim

On May 3, 2016, in the case of Wyandotte Electric Supply Company v Electrical Technology Systems, Inc., the Michigan Supreme Court issued an important opinion regarding “notice” requirements under the Michigan Public Works Act (PWA). The case involved renovation of the Detroit Public Library. KEO & Associates was the general contractor and Westfield Insurance Company supplied KEO with a $1.3 million payment bond as required under PWA. KEO subcontracted with Electrical Technology Systems (ETS) who in turn subcontracted with Wyandotte Electrical Supply for material and supplies.

ETS and Wyandotte had agreed to an open account arrangement, pursuant to which ETS would be liable for attorney fees and time-price differential charges of 1.5% on past due amounts. A time-price differential charge is “the difference between the current cash price of an item and the cost of purchasing the item with credit. A payment made with cash is immediate; a payment made with credit is not. Thus, when a payment is made with credit, the seller [such as Wyandotte] is burdened by a cash-flow interruption. A time-price differential compensates for the increased cost to a seller for credit. It reflects the difference between the credit price and the cash price.”